NWDPRA
PROGRESS REPORT UNDER NATIONAL WATERSHED DEVELOPMENT PROJECT FOR RAINFED AREAS
| S.No | Component/Activities | Unit | Phy | Fin. (Rs. in Lacs) | ||
| Tar. | Ach. | Alloc. | Expdt. | |||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| I) | Management Component | |||||
| A | Administration Cost | |||||
| a) State/District Headquarter | No's | 20 | 6.00 | |||
| b) Watershed Committee (WC) | No's | 34 | 3.40 | |||
| - Salary | - | - | ||||
| - Other Expenses | - | - | ||||
| c) Project implementation Agencies (PIA) | No's | 34 | 3.40 | |||
| - Salary | - | - | ||||
| - Other Expenses | 34 | 10.00 | ||||
| Total (A) :- | 22.80 | |||||
| B | Community Organizations | |||||
| a) Entry point activities of Watershed Committee | No's | 34 | 10.20 | |||
| b) Honorarium to village based community organizers | No's | 34 | 2.00 | |||
| c) Expenses at District Headquarter for publicity, support for production of technology input, support for infomration technology at village level,miscellaneous charges etc | No's | 10 | 5.00 | |||
| Total (B) :- | 17.20 | |||||
| C | Training Programme | |||||
| a) -State level training cost | No's | 1 | 1.00 | |||
| - District level training cost | No's | 20 | 2.00 | |||
| b) PIA-Training cost at identified Institutes | No's | 50 | 0.50 | |||
| Total (C):- | 3.50 | |||||
| Total Management Component:- | 43.50 | |||||
| II) | Development Component | |||||
| A | Natural Resource Management | |||||
| a) Arable Land | ||||||
| - Contour hedges with trenches | Hects. | 2000 | 30.00 | |||
| - Repairs of existing conservation measures | Hects. | 2000 | 8.00 | |||
| - Gully control measures | No's | 2000 | 24.00 | |||
| Support for strengthening of terrace | Hects. | 1000 | 10.00 | |||
| Total (a) :- | 72.00 | |||||
| b) Non Arable Land | ||||||
| 1 | Run off management structure | |||||
| a) Vegetative filter strips | Rmts. | 10000 | 3.00 | |||
| b) Vegetative contour hedges with furrous | Hects. | 1500 | 15.00 | |||
| c) Gully control measures | No's | 500 | 12.50 | |||
| Total (b) :- | 30.50 | |||||
| 2 | c) Water Harvesting Structures | |||||
| a) Dug Out Ponds | No's | 400 | 20.00 | |||
| b) Brush wood check dams | No's | 200 | 6.00 | |||
| c) Roof harvesting structure | No's | 600 | 12.00 | |||
| d) Dryland Horticulture | ||||||
| Planting of Trees | No's | 2E+05 | 20.00 | |||
| Total (c) :- | 58.00 | |||||
| TotalFinancialNonArableLands:- | 88.50 | |||||
| c)DrainageLines | ||||||
| -Bank Stablization | Rmts. | 2000 | 10.00 | |||
| -Upper reaches | ||||||
| a) Brush wood checks | No's | 500 | 1.50 | |||
| b) Loose bolder checks | No's | 100 | 1.50 | |||
| - Middle reaches | ||||||
| a) Loose bolder checks | No's | 50 | 1.50 | |||
| b) Run-off check management ponds | Hects. | 50 | 2.50 | |||
| - Lower reaches | ||||||
| a) Limited number of dug out run-off devices | No's | 20 | 10.00 | |||
| Total (c) :- | 27.00 | |||||
| Total A | 187.50 | |||||
| B | Farm Production System for land owning families | |||||
| a) Establishement of Nurseries & Prod.of seedlings | No's | 10 | 7.50 | |||
| b) Testing & Demonstration of new technologies | ||||||
| i. Kharif | Hects. | 100 | 2.00 | |||
| ii) Rabi | Hects. | 500 | 10.00 | |||
| iii) Vermi Compost Units | No's | 34 | 10.20 | |||
| c) Diversification of production system | ||||||
| i) Planting of Horticulture | No's | 80000 | 24.00 | |||
| ii) Agro-Forestry | No's | 2E+05 | 20.00 | |||
| iii) Organic Farming | No's | 1000 | 2.00 | |||
| iv) Use of Bio-Fertilizers | No's | 2000 | 1.00 | |||
| v) Live stock Management and others | No's/ha | 200 | 2.00 | |||
| Total (B) :- | 78.70 | |||||
| C | 3. Livelihood support system for land-less families | |||||
| a. Houshold Production system | ||||||
| i) Small live stock system | No's | 200 | 5.00 | |||
| ii) Bio-mass based rural Industry activities | No's | 300 | 3.60 | |||
| iii) Others (Service Sector) | No's | 250 | 3.15 | |||
| c.Dairy, Sericulture, Goat breeding, Bee-Keeping, Mushroom cultivation, commercial poultry etc. | No's | 500 | 12.50 | |||
| d. Livestock Management | ||||||
| i) Castration of Scrubulls | Animals | 1000 | 0.40 | |||
| ii) Incentive for Breeding Service | Animals | 1000 | 1.00 | |||
| iii) Provision of Bulls for natural service | Animals | 20 | 1.00 | |||
| iv) Promotion of cultivated fodder | Hects. | 500 | 5.00 | |||
| Total (C):- | 31.65 | |||||
| Total Development Component:- | 297.85 | |||||
| GrandTotal:- | 341.35 | |||||